The complete guide to house extensions
Everything you need to price, plan and control a house extension in the UK — written for homeowners who have never run a building project and do not want to learn the expensive way.
What an extension actually costs
Builders price extensions per square metre of new floor area, then add fixed costs for site setup, drainage, structural work and finishes. In 2026 the national range for a straightforward single storey extension is roughly £1,750–£2,900 per m² excluding VAT, before you fit a kitchen. London and the South East sit 15–30% above that.
The number that matters is not the rate — it is what the rate includes. A £1,800/m² quote that excludes glazing, kitchen, flooring and making good is more expensive than a £2,400/m² quote that includes all four. This is the single most common reason homeowners believe they were 'quoted low and charged high'.
| Extension type | Typical cost (ex VAT) | What usually changes it |
|---|---|---|
| Single storey rear, 20m² | £38,000 – £62,000 | Foundation depth, glazing spec, structural opening |
| Side return, 12m² | £30,000 – £52,000 | Access, party wall, hand-dug foundations |
| Double storey, 40m² total | £70,000 – £110,000 | Roof integration, bathroom above, planning |
| Kitchen extension incl. kitchen | £55,000 – £95,000 | Kitchen specification, glazing, underfloor heating |
Planning permission and permitted development
Many single storey rear extensions fall within permitted development: up to 4m deep on a detached house, 3m on a semi or terrace, or 8m and 6m respectively under the larger home extension prior approval process. Side extensions, two storey work, anything forward of the principal elevation, flats, listed buildings and conservation areas all sit outside it.
Even where you do not need planning permission, apply for a Lawful Development Certificate. It costs a fraction of a planning application and is the document a buyer's solicitor will ask for. Building regulations approval is separate and always required.
- Permitted development rights are sometimes removed by an Article 4 direction or a planning condition on newer estates — check before you design.
- Building over or within 3m of a public sewer needs a build-over agreement from your water company.
- Party Wall Act notices are needed for excavation within 3m of a neighbour's structure, and for work on a shared wall.
Realistic timescales
Design and approvals take longer than construction on most projects. Allow 4–8 weeks for design, 8 weeks for a planning decision, 3–6 weeks for structural design and building control, and 6–10 weeks for party wall awards where neighbours are involved. These overlap, but not entirely.
On site, a single storey extension is typically 10–14 weeks, a double storey 16–24 weeks. Add contingency for weather in winter and for the two things that always take longer: foundations and glazing lead times.
Common mistakes that cost real money
Almost every extension overrun traces back to one of five decisions made before work started.
- Signing a quote based on sketches rather than a specification and drawings. Different builders then price different buildings.
- Accepting provisional sums for kitchen, glazing and flooring. These are placeholders, and they are always lower than what you will choose.
- No contract. For anything over £25,000 use a JCT Home Owner contract or similar — it fixes payment stages, variations and completion.
- Paying too much up front. Staged payments against completed work protect you; a 40% deposit does not.
- Changing your mind after first fix. Variations after the walls are up cost multiples of what they would have cost on paper.
How to compare three builders properly
Give every builder identical drawings, a written specification and the same provisional sums. Ask each to price the same document and to state clearly what is excluded. Then compare exclusions before you compare prices.
If one quote is 25% below the others, it is almost never better value — it is a different scope. Find the missing items. That is what an independent quotation review is for.
Questions to ask builders
- What is excluded from this price, in writing?
- What foundation depth have you allowed, and what happens if we hit clay, roots or a drain?
- Which provisional sums are in the quote, and what allowance do they carry?
- Who pays for the structural engineer, building control and party wall surveyor?
- What are the payment stages, and what must be complete before each one?
- How many weeks on site, and what is your liability if the programme slips?
- Is scaffolding included, and for how many weeks?
- What warranty applies to workmanship, and is any insurance-backed guarantee provided?
Warning signs in a quotation
- A quotation that fits on one page with no exclusions listed.
- A large deposit requested before any materials are ordered.
- No structural engineer involved where beams are clearly needed.
- Reluctance to provide public liability insurance details or previous client references.
- Verbal assurances that 'the kitchen is included' with nothing written down.
- Prices quoted without stating whether VAT applies.
Frequently asked questions
How much does an extension cost per square metre in the UK?
£1,750–£2,900 per m² ex VAT nationally in 2026 for a single storey extension shell and finish, before kitchen or bathroom fit-out. London typically 25–30% higher.
Do I need an architect?
For anything structural, yes — or an architectural technologist. Their drawings are what make three quotations comparable, which usually saves more than the fee.
How much value does an extension add?
It varies by area and is capped by local ceiling prices. Adding a bedroom and bathroom typically returns more than adding floor area to a living space.
Can I live in the house during the work?
Usually yes for a rear extension, but expect six to ten weeks without a functioning kitchen if the work connects to it.
What is a provisional sum?
An allowance for work not yet specified. It is not a fixed price — when the real choice is made, the difference is charged to you.
Independent
We do not sell leads, take commission or work with contractors.
Evidence-linked
Every finding points back to the exact page and wording in your quote.
Private
Your quotation is used to produce your report and nothing else.
Price it with a calculator
Already have a quote?
Upload it to KnowMyQuote and receive a detailed independent comparison showing whether you’re paying too much, too little, or receiving poor value.
- Your documents stay private
- Every finding linked to the wording
- No affiliation with any contractor